Site Transformation and Restructuring
Relocate without losing deliveries
We take operational lead on plant relocation, consolidation and process turnaround, so customer deliveries do not break down during the change.
A relocation rarely fails on the technical side. It fails because deliveries break down during the move. We plan the sequence so that each process chain is only moved once its supply is secured, and we support your team through implementation on the shopfloor.
Our approach
We start by mapping layout, material flow and storage structure and calculating the actual space and capacity required. Before the first relocation stage we review your contractual commitments to customers, so promises and the move plan line up. From that we derive the relocation sequence, based on process chains rather than the calendar. For the transition phase we define advance production and safety stock, so the customer never notices the move. At the new site we support the restart through to stable series production and secure requalification of the parts. Investment, schedule and risk run through a single joint plan, reviewed weekly.
Results
from completed engagements
21,500 square meters
layout and material flow redesigned.
10 % under budget
project completed, all processes relocated within the planned period.
Around 5,000 pallets
external warehousing eliminated entirely.
FAQ
How do you plan a plant relocation without a delivery interruption?
The move is planned by process chains, not by departments. Before every relocation stage the question is how the affected parts reach the customer during that window. Advance production, safety stock or a second source bridge the standstill. Without that preparation the gap opens exactly where it is most expensive.
How long does a production relocation take?
That depends on floor space, the number of machines and whether a new ramp-up is required at the destination. For a full plant relocation of medium size, one to two years is a realistic frame, with the restart through to stable series production taking the larger share. A pure reorganization within an existing site is considerably faster.
How do you maintain delivery capability during a relocation?
Through a transition supply that is in place before the first move. In practice that means advance production into stock, extended run time on the old equipment and special logistics as a fallback. It is important to involve the customer early rather than surprising them with a delay.
How do you minimize risk in a site relocation?
The largest risks are not in logistics, they sit in staffing and qualification at the new site and in requalification of the parts. Both need lead time. A workable fallback for each relocation stage belongs to that, so a delay does not immediately hit deliveries.
What are the most common mistakes in a plant relocation?
Change management is often missing, so deviations only become visible late. Just as often, the effort for training and qualification at the destination is underestimated. In international relocations, language and cultural differences add to that, and systems running in parallel make control harder.
How do you secure quality after a relocation?
Parts and processes have to be re-verified at the new site, usually through PPAP submission and evidence of process capability. The effort for this is regularly planned too small. Starting requalification only after the move costs weeks.
How do you consolidate multiple sites without a production stop?
First establish which scopes can actually be combined, measured against equipment, qualification and customer approvals. Then relocate in stages, always with supply secured for running orders. Existing customer contracts are the real constraint, not floor space.
What is the difference between restructuring, turnaround, and transformation?
Restructuring changes the structures and shape of a company. A turnaround starts when the financial situation is already critical. Transformation describes the longer-term rebuild of processes and business model. We work on operational implementation in all three cases, not on the financial structure.
Cases
A relocation is not a move, it is an intervention in a running supply chain. If a relocation or consolidation is ahead of you, we will look at the process chains before the first date is fixed.