Site Transformation · Production and Logistics
21,500 square meters relocated, 10 % under budget
Production operation with manufacturing spread across several floors, limited space and outsourced warehousing.
Starting situation
Production was spread across several floors, which led to a shortage of space and long transport routes. Around 5,000 pallets were stored externally and had to be transported daily.
Measures
We redesigned the layout including material flow across 21,500 square meters and installed a narrow-aisle high-bay system, including supplier selection. With the new material flow system, external warehousing became unnecessary.
Results
21,500 square meters
layout and material flow redesigned.
10 % under budget
project completed, all logistics and production processes relocated within the planned period.
External warehousing of around 5,000 pallets eliminated.
Our mandates
Project leadership for the plant relocation, project management specialist.