Produce stably, deliver predictably

We analyze your processes, identify the sources of loss and implement the improvement directly in production. First results are achievable in the short term.

An unstable process costs twice, first through scrap and then through special transport. We go onto the shopfloor, measure the actual loss and work with your team until the process runs without extra effort. Then we hand over.

Our approach

We start by establishing the real condition rather than the reported one, through a line walk on the shopfloor, an analysis of your data and a look at contracts, deliveries and staffing. We then separate capacity, quality and organizational losses and prioritize by impact. Measures are implemented directly in production, from setup time reduction to maintenance and shift models. In parallel we build up shopfloor management, so deviations become visible at the board instead of in the monthly review. Where staffing is short, we set up qualification.

Results

from completed engagements

85 % OEE

target value reached within four months, from a significantly lower starting level.

100 %

on-time delivery of all customer orders within four months.

Four-shift system and training center

established to secure capacity and qualification for the long term.

View the case

FAQ

How do you secure a series ramp-up?

A ramp-up succeeds when product, equipment, people and parts supply reach maturity at the same time. What matters is measuring maturity in each area early and closing gaps before start of production. Correcting course only during the ramp-up means running on special transport instead of a stable process.

How long does a series ramp-up take?

From pre-series to stable series production, twelve to twenty-four months is typical in the automotive industry, depending on product complexity and the number of variants. The critical phase is the transition from tooling into series production, because quality and volume are demanded at the same time.

How do you improve OEE quickly?

The fastest effects come from setup time reduction, preventive maintenance on bottleneck equipment and cutting scrap and rework. This requires an honest loss assessment, because many machines lose more time to minor stoppages than to visible breakdowns.

What is a good OEE value?

85 % is regarded as world class, calculated from 90 % availability, 95 % performance and 99.9 % quality. In discrete manufacturing many lines actually sit at around 60 %. Consistent, comparable measurement matters more than the absolute figure.

How do you stabilize an unstable production process?

Stability first, capability second. Variation and disturbance factors are reduced first, so the process becomes reproducible at all. Only then can process capability be assessed and secured for the long term. Reversing that order produces figures that mean nothing.

What Cpk value indicates a capable process?

For standard characteristics a Cpk of at least 1.33 is the requirement, for safety-critical characteristics at least 1.67. A Cpk of 1.33 corresponds to roughly four sigma. The assessment only holds if the process was stable beforehand.

What should you do about supply shortages in series production?

Secure deliveries to the customer first, if necessary through special transport or a replacement source. In parallel, locate the bottleneck precisely, whether it sits in material, capacity or quality. Only then do permanent measures take hold. Ramping up special logistics alone buys time without addressing the cause.

How does shopfloor management work?

It is a daily control loop directly on the shopfloor. Deviations are made visible at the board, causes are named, measures are assigned with an owner and a date, and then followed up. It becomes effective when the meeting stays short, happens daily and the manager is present.

Cases

A process that quietly loses money does not improve on its own. If you want to know where your losses actually occur, we will look at the shopfloor.